Road Realignment, Barkley & Titus Intersection, Fort Carson, CO
  • New Electrical Substation
  • Zero lost time accidents or incidents

 

 

This multi-faceted project (road, bridge, utilities) included asphalt demolition and installation of 1.6 miles of new paving with support utilities, including installation of stormwater, sanitary sewer, gas main, water main, industrial waste, and underground electrical and communication lines.

 

  • New Electrical Substation
  • 30 electric vaults
  • 30 communications vaults (including 24,000 ft.      of concrete duct bank)
  • 2 feed circuits
  • 7 feeder circuits into the substations